Client: CollinsWoerman
Location: Portland, OR
Size: Hospital - 340,000 SF; MOB - 180,000 SF; Below Grade Parking - 50,000 SF; Central Utility Plant - 16,000 SF
Construction cost: $235M
New greenfield hospital and medical office building currently under design. Project is a 6-story, 175-bed community hospital with attached medical office building, one level of below grade parking garage, and adjacent central utility plant. Project is using an Integrated Project Delivery (IPD) system. Energy Use Index (EUI) for the hospital is targeted to be 150,000 BTU/SF/YR, with an EnergyStar rating of 75 or better, measured at completion and one year after.
Client: Good Sam Design Collaborative (a joint venture of Clark/Kjos Architects and Giffin Bolte Jurgens Architects)
Location: Puyallup, WA
Size: 350,000 SF
Construction cost: $280M
New nine-story patient tower with new private patient rooms; entrance lobby and drop off area; and emergency, imaging, and surgery departments. A new central utility plant to serve the hospital is also part of the project. Project is being designed using Revit MEP. This project is tracking LEED-NC Silver certification.
Client: Giffin Bolte Jurgens Architects
Location: Tacoma, WA
Size: 144,000 SF
Construction cost: $64M
Major five-story hospital expansion and remodel of the emergency department and radiation oncology, new urgent care spaces, new parking, and additional shelled spaces. Sustainable features for potential LEED credits are integrated with Green Guide for Health Care credits to help guide the design. This project is on track for LEED-NC Silver certification.
Client: Mithun (Seattle) / Pfeiffer Partners, Inc. (Los Angeles)
Location: Seattle, WA
Size: 130,000 SF
Construction cost: $35M
Renovations to all six levels of the existing 90,000 SF library and construction of a 40,000 SF addition. Extensive energy modeling, life cycle cost assessment, and a holistic approach with code officials were necessary to achieve the LEED rating. Mechanical systems include displacement ventilation, chilled beams, controlled environment, and heat recovery to support program spaces including stacks, digital commons, media production, and several focused reading rooms. The project's energy use index exceeds the 2030 Challenge goal for 2010. It is on track to obtain a LEED-NC Gold rating.
Client: Bohlin Cywinski Jackson
Location: Blaine, WA
Size: 74,000 SF
Construction cost: $49M
Complete replacement the Port-of-Entry facility, that received an Honor Award in Architecture On-the-Boards New Construction from the GSA 2006 Design Awards competition. This project is tracking a LEED-NC Silver rating.
Client: NAC Architecture
Location: Oak Harbor, WA
Size: 200,000 SF renovation; 30,000 SF addition
Construction cost: $54M
Major renovation and expansion of an existing high school, including a new two-story wing and the complete replacement of the mechanical systems. This is a multi-phased project that is being constructed while occupied. Mechanical systems include 100% outside air and displacement ventilation in classrooms, sophisticated industrial technologies building, and a grand auditorium will full production stage. The project is being designed for certification under the Washington State Sustainable Schools Protocol, and has achieved the "Designed to Earn the Energy Star" designation.
Client: Mahlum Architects
Location: Bellingham, WA
Size: 134,000 SF
Construction cost: $37M
Complete renovation of existing historic building to provide spaces for classrooms, computer labs, instructional space, offices, and support facilities. The project is using a GC/CM process. Mechanical systems include 100% outside air and chilled beams in specific classrooms, high efficiency chilled water system, and a hydronic heating system generated from campus steam. Project is being designed using Revit MEP. The University is targeting a LEED-NC Silver rating for this building.
Client: LMN Architects
Location: Seattle, WA
Size: 138,000 SF
Construction cost: $22M
Renovation to convert existing museum spaces in the 800 Pike portion of the convention center facility to convention center uses. The project is targeting LEED-CI Silver certification.
Client: LMN Architects
Location: Seattle, WA
Size: 49,000 SF
Construction cost: $22M
Renovation of existing historic Naval Reserve Building at south end of Lake Union. Project will convert the antiquated open structure facility into a state-of-the-art museum with exhibit areas, environmentally-controlled spaces, offices, classroom, and retail. The mechanical systems will include displacement ventilation, radiant cooling panels, high efficient chilled water system, and acoustically engineering air systems. The project is targeting LEED-CI certification.
Client: NBBJ
Location: Renton, WA
Size: 152,000 SF Building; 127,000 SF Parking
Construction cost: $110M
New hospital tower to house an emergency department, intensive care unit, additional patient floors, and underground parking.
Client: HDR, Inc.
Location: Wenatchee, WA
Size: 264,000 SF (new tower, renovation of existing hospital spaces, CUP, professional office building); parking garage – 447 stalls (2 stories)
Construction cost: $107M
Major facility expansion with a new bed tower, renovation of existing hospital spaces, central utility plant expansion, new professional office building, and new parking garage.
Client: Zimmer Gunsul Frasca Architects
Location: Portland, OR
Size: 330,000 SF
Construction cost: $143.4M
Programming, conceptual planning, and design for new pediatric hospital with four acute care units, Pediatric Intensive Care Unit (PICU), and Neonatal Intensive Care Unit (NICU), as well as pediatric emergency and diagnostics departments. Hospital consists of one below grade level, nine floors above grade, and a mechanical penthouse level. The project is using the Green Guide for Health Care as a basis for a sustainable approach to healthcare design.
Client: Zimmer Gunsul Frasca Architects
Location: Everett, WA
Size: 730,000 SF
Construction cost: $385M
New 400+ bed critical care tower and new central utility plant being designed to serve the entire campus. Project includes surgeries, pre- and post-operative support, ICU, and standard patient care spaces; a new emergency department; and features a unique pandemic supply/exhaust system. The facility is using the Green Guide for Health Care as a basis for a sustainable approach to healthcare design.
Client: Pfeiffer Partners, Inc
Location: Bellevue, WA
Size: 135,000 SF
Construction cost: $110M
New 2,000-seat, multi-tiered community performing arts facility with an auditorium, stage, back-of-house spaces, and front-of-house spaces, as well as a 3-story underground parking garage. Mechanical systems include an underfloor displacement system for the theater seating area and orchestra pit, chilled beam system with 100% outside air system serving dressing room areas, and a green roof. Project is being designed using Revit MEP. This project is tracking LEED-NC certification.